Sinking Fund / Bond Projects
Sinking Fund Projects
2017-2018 Projects
District
- Security Upgrade- The Lockout Boot Company
Betsie Valley
- Replace Gate
- Unit Ventilator Controls
- Drinking Fountain
Crystal Lake
- New Kitchen Flooring
- Fire Suppression System in Kitchen
- Kitchen Hood
- Kitchen Exhaust
- Ventilation System
- New Kitchen Plumbing, Cement Pad
- New Faucets and Valves
- Waterheater
- Replaced Boiler Components
High School
- New Hallways
- Roof Top Heating/Air Conditioning Unit
- Removal of track surface
- New Fence and Gates Football Field
2018-2019 Projects
District
- 124 Chromebooks
- 124 Chromebook Licenses
- 2 Chromebook Carts
Betsie Valley
- Playground Equipment
- Boiler Controls, Wiring, and Venting
- Replacement of Lights
- Water Filters
- Water Cooler Bottle Fill
- Door Replacement
- Dome Cameras
- DVR for Security Cameras
Crystal Lake
- Building Repairs
- Playground Door Lock
- Playground Equipment
- Water Cooler Bottle Fill Station
High School
- Hallway Flooring West Wing
- Drinking Faucets
- Gym Floor
- 16 Channel DVR for Camera System
- Press Box Remodel
- Fire Suppression System
- Fire Alarm
- Maintenance Shop Door
- Bleacher Repairs
- Door and Door Jamb Replacement welding Shop
- Fence Repairs and new Gate
- Replacement of Gate Valves
- Disposal Field Replacement
Lake Ann
- Gym Floor
- Air Handler Repairs
- Playground Equipment
- Water Cooler Bottle Fill Station
Middle School
- Gym Floor
- Building Repairs
- Egress Fire Doors
- Door Locks
- Water Cooler Bottle Fill Station
2019-2020 Projects
District
- Chromebooks
- Charging Cart
- Signage for Boot System
- New Sign
- Chromebook Cases
- Hard Drives
- Insulation
Betsie Valley
- New Hallway Flooring
- New Gym/Cafeteria Flooring
- New Classroom Flooring
- New Carpeting 2 rooms
- Flooring/Ceiling Project
- Replace Window Screens
- Door and Door Jamb Replacement Boiler Room
- Inside Doors Lock Cylinder Replacement
- Steam Coil Replacement
- Washer and Dryer Hookup
Benzie Academy
- New Flooring
- Signage
- Crystal Lake
- Projector
- Playground Equipment
- Replace Sewer Line
- 2 security cameras
- Washer and Dryer Hookup
High School
- Gym Floor
- Refinish Stage Flooring
- Resurface Baseball and Softball Field
- Garage Door for Green House
- Plumbing Updates
- Electrical Upgrades to Woodshop
- Science Lab Duct Install
- Replace Steam Coil
- Football Field
- Boiler Feed Tank Replacement
- New Sidewalks and Spillways North side
- Fire Door Replacement
- Replace Damaged Fascia
- Installed Cell Foam Insulation Auditorium
Lake Ann
- New Classroom Flooring
- Playground Equipment
- Fencing/Gates
- Curb and Sidewalk Replacement
- Door and Door Jamb Replacement Boiler Room
Middle School
- Gym Floor
Bond Project Updates
2020 Bond Updates
Looking to the future of Benzie County Central Schools……..
No first update about the 2020 Bond could begin without saying thank you. Thank you to everyone who has supported the bond and to anyone who has come on board to offer their time and experiences to make the next several years of bond work a success. Since the November 3rd passage of the bond, we have been hard at work ramping up all of the people and processes that it will take to accomplish the goals of the bond projects; district-wide improvements, and identifying the ongoing building, facility, and site issues.
Questions regarding our upcoming bond projects?
Please contact Superintendent, Amiee Erfourth. [email protected].
Information will continue to be updated. We thank you for your continued support of Benzie County Central Schools
Bond Project Documents
CORE Team Minutes
Projects in Action: District-Wide Projects
-
Click to see a larger version Auditorium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Auditorium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Auditorium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Auditorium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Auditorium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Auditorium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version New Roof Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Central Business Office Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Central Business Office Skip to end of gallery Skip to start of gallery
Projects in Action: HS Gymnasium / Locker Rooms
-
Click to see a larger version Gymnasium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Gymnasium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Gymnasium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Gymnasium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Gymnasium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Gymnasium Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Locker Rooms Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Locker Rooms Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Locker Rooms Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Locker Rooms Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Locker Rooms Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Locker Rooms Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Locker Rooms Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Locker Rooms Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Locker Rooms Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Locker Rooms Skip to end of gallery Skip to start of gallery
Projects in Action: Lake Ann Elementary
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
Projects in Action: Homestead Hills Elementary
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
Projects in Action: Weight Room Addition
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
Projects in Action: Cafeteria
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery
-
Click to see a larger version Skip to end of gallery Skip to start of gallery